10 Small to Medium Sized Network Security Solution part 10



Project Plan and Timeline

Project Deliverable or Milestone

Duration
Planned Start Date

Planned End Date
Pen test existing network
1 day
06/05/15
06/05/15
Report results
1 day
06/06/15
06/06/15
Determine HW requirements
1 day
06/07/15
06/07/15
Determine SW requirements
1 day
06/08/15
06/08/15
Determine Configuration
1 day
06/09/15
06/09/15
Determine Administration
1 day
06/10/15
06/10/15
Outline steps to harden network security
1 day
06/11/15
06/11/15
Build the prototype
5 days
06/12/15
06/16/15
Implement following the resulting outline
1 day
06/17/15
06/17/15
Pen test new network security
1 day
06/18/15
06/18/15
Report results
1 day
06/19/15
06/19/15
Educate the public
1 day
06/20/15
06/20/15



The project progressed basically as outlined with the resulting deliverables and few exceptions. I explain any adjustments and the rationale behind those adjustments in the next project development section of my report.